2018-04-17 Retrospektive
Retrospective
What did we do well?
- Integration from the side of Novatec was fast
- Good progress
- Distribution of the tasks was good
What should we have done better?
- Should integrate all Tasks until Sprint Review
- Try to ensure a high quality
- Correct wrong and add new important aspects in the Wiki
- Team communication was not as good as before
Actions
- Correct wrong and add important information to the Wiki. Responsible: TEAM
- Ensure that REST-API-Documentation is up to date. Responsible: Backend Developer
- Stick to the Requirements of the Definition of Done. Responsible: Marcus Danzer
- Optimize the scheduling in order to integrate Sprint scope. Responsible: Marcel Sailer
- Distribute the Frontend tasks better. Responsible: Damian Bocklet
- Establish a regular developer meeting. Responsible: Tatiana Signe